News Breaks | | | | February 26, 2013 | | 07:41 EDT |  | AG | First Majestic expects to increase FY13 production from FY12 Production in FY13 is expected to increase from 2012 levels with the following upcoming developments: at Del Toro, production from the 1,000 tpd flotation circuit commenced in January 2013 and construction of the 1,000 tpd cyanidation circuit expected to commence production in the third quarter of 2013; at La Guitarra, a new ball mill and flotation cells will increase capacity from 350 tpd to 500 tpd during March 2013; at San Martin, the cyanidation plant is being expanded which will increase capacity from 950 tpd to 1,300 tpd in the Q2 of FY13. | |
|